APRIL 2018
Sunday, April 22 – Saturday, April 28, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 28th
Sunday, April 22, 2018
-
No scheduled construction activity.
Monday, April 23, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo and install sidewalk from Thomas Circle to N Street NW (east side).
Tuesday, April 24, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo and install sidewalk from Thomas Circle to N Street NW (east side).
Wednesday, April 25, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo and install sidewalk from Thomas Circle to N Street NW (east side).
Thursday, April 26, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo existing curb and gutter from N Street to 1323 (east side).
Friday, April 27, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo existing curb and gutter from N Street to 1323 (east side).
Saturday, April 28, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo existing curb and gutter from N Street to 1323 (east side).
Sunday, April 15 – Saturday, April 21, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 21st)
Sunday, April 15, 2018
-
No scheduled construction activity.
Monday, April 16, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
Tuesday, April 17, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
Wednesday, April 18, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).
-
Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).
Thursday, April 19, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).
-
Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).
Friday, April 20, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).
-
Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).
Saturday, April 21, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).
-
Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).
Sunday, April 8 – Saturday, April 14, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 14th)
Sunday, April 8, 2018
-
No scheduled construction activity.
Monday, April 9, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Tuesday, April 10, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Layout curb from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Wednesday, April 11, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Thursday, April 12, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Friday, April 13, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Saturday, April 14, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Sunday, April 1 – Saturday, April 7, 2018:
Scheduled Activity, Weather Permitting
(There is no work currently scheduled for Saturday, April 7th)
Sunday, April 1, 2018
-
No scheduled construction activity.
Monday, April 2, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Tuesday, April 3, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Wednesday, April 4, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Thursday, April 5, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Friday, April 6, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Saturday, April 7, 2018
-
No scheduled construction activity.