APRIL 2018

Sunday, April 22 – Saturday, April 28, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, April 28th

Sunday, April 22, 2018
  • No scheduled construction activity.

Monday, April 23, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).

  • Installation of catch basins from N Street to Rhode Island Avenue NW (east side).

  • Demo and install sidewalk from Thomas Circle to N Street NW (east side).

Tuesday, April 24, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).

  • Installation of catch basins from N Street to Rhode Island Avenue NW (east side).

  • Demo and install sidewalk from Thomas Circle to N Street NW (east side).

Wednesday, April 25, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).

  • Installation of catch basins from N Street to Rhode Island Avenue NW (east side).

  • Demo and install sidewalk from Thomas Circle to N Street NW (east side).

Thursday, April 26, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).

  • Installation of catch basins from N Street to Rhode Island Avenue NW (east side).

  • Demo existing curb and gutter from N Street to 1323 (east side).

Friday, April 27, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).

  • Installation of catch basins from N Street to Rhode Island Avenue NW (east side).

  • Demo existing curb and gutter from N Street to 1323 (east side).

Saturday, April 28, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).

  • Installation of catch basins from N Street to Rhode Island Avenue NW (east side).

  • Demo existing curb and gutter from N Street to 1323 (east side).

​​

Sunday, April 15 – Saturday, April 21, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, April 21st)

Sunday, April 15, 2018

  • No scheduled construction activity.

Monday, April 16, 2018

  • Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).

Tuesday, April 17, 2018

  • Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).

Wednesday, April 18, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).

  • Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).

Thursday, April 19, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).

  • Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).

Friday, April 20, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).

  • Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).

Saturday, April 21, 2018

  • Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).

  • Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).

Sunday, April 8 – Saturday, April 14, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, April 14th)

Sunday, April 8, 2018

  • No scheduled construction activity.

Monday, April 9, 2018

  • Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).

  • Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).

Tuesday, April 10, 2018

  • Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).

  • Layout curb from Rhode Island Avenue to P Street NW (east side).

  • Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).

 

Wednesday, April 11, 2018

  • Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).

  • Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).

 

Thursday, April 12, 2018

  • Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).

  • Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).

Friday, April 13, 2018

  • Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).

  • Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).

Saturday, April 14, 2018

  • Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).

  • Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).

Sunday, April 1 – Saturday, April 7, 2018: 
Scheduled Activity, Weather Permitting 

(There is no work currently scheduled for Saturday, April 7th)

Sunday, April 1, 2018
  • No scheduled construction activity.

Monday, April 2, 2018

  • Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).

  • Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).

  • Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).

  • Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).

 

Tuesday, April 3, 2018

  • Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).

  • Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).

  • Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).

  • Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).

 

Wednesday, April 4, 2018

  • Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).

  • Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).

  • Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).

  • Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).

 

Thursday, April 5, 2018

  • Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).

  • Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).

  • Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).

  • Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).

 

Friday, April 6, 2018

  • Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).

  • Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).

  • Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).

  • Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).

Saturday, April 7, 2018

  • No scheduled construction activity.