MARCH 2020
Sunday, March 22 – Saturday, March 28, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, March 28th.
Sunday, March 22, 2020
-
No scheduled construction activity.
Monday, March 23 - Friday, March 27, 2020
-
Pulling cables at Florida Avenue NW between 13th and 14th Street (occurs during overnight hours).
-
Paving work on 14th Street.
-
Tree planting and landscaping.
-
Pulling cables at Florida Avenue NW between 13th and 14th Street (occurs during overnight hours starting on Friday after 7pm through Sunday).
Saturday, March 28, 2020
-
Continued pulling of cables at Florida Avenue NW between 13th and 14th Street (also occurs during overnight).
Sunday, March 15 – Saturday, March 21, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, March 21st.
Sunday, March 15, 2020
-
No scheduled construction activity.
Monday, March 16 - Friday, March 20, 2020
-
Milling and paving from U Street NW to R Street NW.
-
Work on Bus Island at T Street NW.
-
Installation of PCC Base from U Street NW to T Street NW.
-
Tree planting and landscaping.
-
Installation of conduits on 14th Street and Wallach Place NW.
-
Installation of fixtures.
-
Removal of streetlights and foundations.
-
Splicing manholes from T Street to Florida Avenue NW.
-
Street light switchovers.
-
Installation of communication cable.
-
Pulling cable at Rhode Island Avenue NW between 14th Street and 15th Street (occurs during overnight hours starting on Friday after 7pm through Sunday).
Saturday, March 21, 2020
-
Milling and paving.
-
Installation of fixtures.
-
Splicing manholes from T Street to Florida Avenue NW.
-
Street light switchovers.
-
Installation of communication cable.
-
Continued pulling of cable at Rhode Island Avenue NW between 14th Street and 15th Street (also occurs during overnight).
Sunday, March 8 – Saturday, March 14, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, March 14th.
Sunday, March 8, 2020
-
No scheduled construction activity.
Monday, March 9 - Friday, March 13, 2020
-
Base repair at R Street NW.
-
Work on Bus Island at T Street NW.
-
Work on water line (T Street to U Street NW).
-
Installation of fixtures.
-
Removal of streetlights and foundations from Swann Street to W Street NW.
-
Splicing manholes from T Street to Florida Avenue NW.
-
Street light switchovers.
Saturday, March 14, 2020
-
Installation of fixtures.
Sunday, March 1 – Saturday, March 7, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, March 1st.
Sunday, March 1, 2020
-
No scheduled construction activity.
Monday, March 2 - Friday, March 6, 2020
-
Base repair at R Street NW.
-
Work on Bus Island at R Street NW.
-
Work on water line (T Street to U Street NW).
-
Installation of fixtures.
-
Splicing manholes from T Street to Florida Avenue NW.
-
Street light switchovers.
Saturday, March 7, 2020
-
Installation of fixtures.
-
Street light switchovers.