top of page

MARCH 2020

Sunday, March 22 – Saturday, March 28, 2020: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, March 28th.

Sunday, March 22, 2020

  • No scheduled construction activity.

Monday, March 23 - Friday, March 27, 2020

  • Pulling cables at Florida Avenue NW between 13th and 14th Street (occurs during overnight hours).

  • Paving work on 14th Street.

  • Tree planting and landscaping.

  • Pulling cables at Florida Avenue NW between 13th and 14th Street (occurs during overnight hours starting on Friday after 7pm through Sunday).

Saturday, March 28, 2020

  • Continued pulling of cables at Florida Avenue NW between 13th and 14th Street (also occurs during overnight).

Sunday, March 15 – Saturday, March 21, 2020: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, March 21st.

Sunday, March 15, 2020

  • No scheduled construction activity.

Monday, March 16 - Friday, March 20, 2020

  • Milling and paving from U Street NW to R Street NW.

  • Work on Bus Island at T Street NW.

  • Installation of PCC Base from U Street NW to T Street NW.

  • Tree planting and landscaping.

  • Installation of conduits on 14th Street and Wallach Place NW.

  • Installation of fixtures. 

  • Removal of streetlights and foundations.

  • Splicing manholes from T Street to Florida Avenue NW.

  • Street light switchovers. ​

  • Installation of communication cable.

  • Pulling cable at Rhode Island Avenue NW between 14th Street and 15th Street (occurs during overnight hours starting on Friday after 7pm through Sunday). 

Saturday, March 21, 2020

  • Milling and paving.

  • Installation of fixtures. 

  • Splicing manholes from T Street to Florida Avenue NW.

  • Street light switchovers. ​

  • Installation of communication cable.

  • Continued pulling of cable at Rhode Island Avenue NW between 14th Street and 15th Street (also occurs during overnight). 

Sunday, March 8 – Saturday, March 14, 2020: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, March 14th.

Sunday, March 8, 2020

  • No scheduled construction activity.

Monday, March 9 - Friday, March 13, 2020

  • Base repair at R Street NW.

  • Work on Bus Island at T Street NW.

  • Work on water line (T Street to U Street NW).

  • Installation of fixtures. 

  • Removal of streetlights and foundations from Swann Street to W Street NW.

  • Splicing manholes from T Street to Florida Avenue NW.

  • Street light switchovers. ​

Saturday, March 14, 2020

  • Installation of fixtures. ​

Sunday, March 1 – Saturday, March 7, 2020: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, March 1st.

Sunday, March 1, 2020

  • No scheduled construction activity.

Monday, March 2 - Friday, March 6, 2020

  • Base repair at R Street NW.

  • Work on Bus Island at R Street NW.

  • Work on water line (T Street to U Street NW).

  • Installation of fixtures. 

  • Splicing manholes from T Street to Florida Avenue NW.

  • Street light switchovers. ​

Saturday, March 7, 2020

  • Installation of fixtures. 

  • Street light switchovers. ​

bottom of page