Sunday, April 28 – Saturday, May 4, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, May 4th.

Sunday, April 28, 2019

  • No scheduled construction activity.

 

Monday, April 29 - Wednesday, May 1, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).

  • Installation of fire hydrants at W Street, V Street and S Street NW. 

  • Installation of streetlight and traffic signal foundations at S Street NW and T Street NW.

  • Installation of catch basins at T Street NW (southwest and northwest corners). 

  • Reconnecting for water service at R Street to U Street (west side).

  • Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at R Street, S Street, T Street and Florida Avenue NW.

  • Installation of TEC foundation and cabinet at the SE corner of U Street NW.

Thursday, May 2, 2019 - Saturday, May 4, 2019

  • All of the above activities with the exception of the installation of TEC foundation and cabinet at the SE corner of U Street NW.

Sunday, April 21 – Saturday, April 27, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, April 27th.

Sunday, April 21, 2019

  • No scheduled construction activity.

 

Monday, April 22 - Saturday, April 27, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).

  • Installation of fire hydrants at W Street, V Street, S Street, Church Street and Florida Avenue NW. 

  • Installation of streetlight and traffic signal foundations at S Street NW and T Street NW.

  • Installation of catch basins at Corcoran Street and T Street NW (southwest and northwest corners). 

  • Reconnecting for water service at R Street to U Street (west side).

  • Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at R Street, S Street, T Street and Florida Avenue NW.

Sunday, April 14 – Saturday, April 20, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, April 20th.

Sunday, April 14, 2019

  • No scheduled construction activity.

 

Monday, April 15 - Friday, April 19, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from V Street to Florida Avenue NW (west side).

  • Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).

  • Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW. 

  • Watermain work at R Street NW (testing and utility markings). 

  • Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.

  • Installation of TEC foundation and cabinet at the SE corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, April 20, 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.

Sunday, April 7 – Saturday, April 13, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, April 13th.

Sunday, April 7, 2019

  • No scheduled construction activity.

Monday, April 8 - Friday, April 12, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks at 14th and U Street (east and west side).

  • Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).

  • Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.

  • Roadway repair from V Street to Florida Avenue NW. These repairs will be done in a block by block sequence (west side).

  • Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.

  • Installation of TEC cabinet at the SE corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, April 13, 2019

  • ll of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.

Sunday, March 31 – Saturday, April 6, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, April 6th.

Sunday, March 31, 2019

  • No scheduled construction activity.

Monday, April 1 - Friday, April 5, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks at 14th and U Street (east and west side).

  • Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).

  • Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.

  • Roadway repair from V Street to Florida Avenue NW. These repairs will be done in a block by block sequence (west side).

  • Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.

  • Installation of TEC cabinet at the SE corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, April 6, 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.