Sunday, April 28 – Saturday, May 4, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, May 4th.
Sunday, April 28, 2019
-
No scheduled construction activity.
Monday, April 29 - Wednesday, May 1, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrants at W Street, V Street and S Street NW.
-
Installation of streetlight and traffic signal foundations at S Street NW and T Street NW.
-
Installation of catch basins at T Street NW (southwest and northwest corners).
-
Reconnecting for water service at R Street to U Street (west side).
-
Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at R Street, S Street, T Street and Florida Avenue NW.
-
Installation of TEC foundation and cabinet at the SE corner of U Street NW.
Thursday, May 2, 2019 - Saturday, May 4, 2019
-
All of the above activities with the exception of the installation of TEC foundation and cabinet at the SE corner of U Street NW.
Sunday, April 21 – Saturday, April 27, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 27th.
Sunday, April 21, 2019
-
No scheduled construction activity.
Monday, April 22 - Saturday, April 27, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrants at W Street, V Street, S Street, Church Street and Florida Avenue NW.
-
Installation of streetlight and traffic signal foundations at S Street NW and T Street NW.
-
Installation of catch basins at Corcoran Street and T Street NW (southwest and northwest corners).
-
Reconnecting for water service at R Street to U Street (west side).
-
Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at R Street, S Street, T Street and Florida Avenue NW.
Sunday, April 14 – Saturday, April 20, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 20th.
Sunday, April 14, 2019
-
No scheduled construction activity.
Monday, April 15 - Friday, April 19, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from V Street to Florida Avenue NW (west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.
-
Watermain work at R Street NW (testing and utility markings).
-
Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.
-
Installation of TEC foundation and cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, April 20, 2019
-
All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.
Sunday, April 7 – Saturday, April 13, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 13th.
Sunday, April 7, 2019
-
No scheduled construction activity.
Monday, April 8 - Friday, April 12, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks at 14th and U Street (east and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.
-
Roadway repair from V Street to Florida Avenue NW. These repairs will be done in a block by block sequence (west side).
-
Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.
-
Installation of TEC cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, April 13, 2019
-
ll of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.
Sunday, March 31 – Saturday, April 6, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 6th.
Sunday, March 31, 2019
-
No scheduled construction activity.
Monday, April 1 - Friday, April 5, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks at 14th and U Street (east and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.
-
Roadway repair from V Street to Florida Avenue NW. These repairs will be done in a block by block sequence (west side).
-
Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.
-
Installation of TEC cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, April 6, 2019
-
All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.