MARCH 2019

Sunday, March 24 – Saturday, March 30, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, March 30th.

Sunday, March 24, 2019

  • No scheduled construction activity.

Monday, March 25 - Friday, March 29, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks at 14th and U Street (east and west side).

  • Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).

  • Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.

  • Roadway repair from V Street to Florida Avenue NW. These repairs will be done in a block by block sequence (east and west side).

  • Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.

  • Installation of TEC cabinet at the SE corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, March 30, 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.

Sunday, March 17 – Saturday, March 23, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, March 23rd.

Sunday, March 17, 2019

  • No scheduled construction activity.

Monday, March 18 - Friday, March 22, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from R  Street to S Street NW (west side).

  • Demolition and installation of sidewalks from P Street to Corcoran Street NW (east side)

  • Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).

  • Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.

  • Roadway repair from U Street to Florida Avenue NW. These repairs will be done in a block by block sequence (east side and west side).

  • Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.

  • Installation of foundation and TEC cabinet at the SE corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, March 23, 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.

Sunday, March 10 – Saturday, March 16, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, March 16th.

Sunday, March 10, 2019

  • No scheduled construction activity.

Monday, March 11 - Friday, March 15, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from P Street to Q Street NW (west side).

  • Demolition and installation of sidewalks from P Street to Corcoran Street NW (east side)

  • Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).

  • Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.

  • Roadway repair from U Street to Florida Avenue NW. These repairs will be done in a block by block sequence (east side and west side).

  • Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at R Street, S Street, T Street, W Street and Florida Avenue NW.

  • Installation of foundation and TEC cabinet at the SE corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, March 16, 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.

  • Additional activity:  Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Sunday, March 3 – Saturday, March 9, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, March 9th.

Sunday, March 3, 2019

  • No scheduled construction activity.

Monday, March 4 - Friday, March 8, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from P Street to R Street NW (west side).

  • Installation of electrical conduit and manholes at U Street NW (east and west side).

  • Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.

  • Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.

  • Installation of traffic control cabinets at W Street, R Street, S Street, T Street and Florida Avenue NW.

  • Installation of foundation and TEC cabinet at the SE corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, March 9, 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.

  • Additional activity:  Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).