AUGUST 2018
Sunday, August 26 – Saturday, September 1, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, September 1st)
Sunday, August 26, 2018
-
No scheduled construction activity.
Monday, August 27, 2018
-
Installation of electrical conduit from Q Street to Corcoran Street NW (west side).
-
Installation of electrical manholes from Q Street to Corcoran Street NW (west side).
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
Tuesday, August 28, 2018
-
Installation of electrical conduit from Q Street to Corcoran Street NW (west side).
-
Installation of electrical manholes from Q Street to Corcoran Street NW (west side).
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
Wednesday, August 29, 2018
-
Installation of electrical conduit from Q Street to Corcoran Street NW (west side).
-
Installation of electrical manholes from Q Street to Corcoran Street NW (west side).
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
Thursday, August 30, 2018
-
Installation of electrical conduit from Q Street to Corcoran Street NW (west side).
-
Installation of electrical manholes from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
Friday, August 31, 2018
-
Installation of electrical conduit from Q Street to Corcoran Street NW (west side).
-
Installation of electrical manholes from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
Saturday, September 1, 2018
-
No scheduled construction activity.
Sunday, August 19 – Saturday, August 25, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, August 25th)
Sunday, August 19, 2018
-
No scheduled construction activity.
Monday, August 20, 2018
-
Installation of electrical conduit from Rhode Island Avenue to P Street NW (west side).
-
Installation of electrical manholes from Rhode Island Avenue to P Street NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Tuesday, August 21, 2018
-
Installation of electrical conduit from Rhode Island Avenue to P Street NW (west side).
-
Installation of electrical manholes from Rhode Island Avenue to P Street NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Wednesday, August 22, 2018
-
Installation of electrical conduit from Rhode Island Avenue to P Street NW (west side).
-
Installation of electrical manholes from Rhode Island Avenue to P Street NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Thursday, August 23, 2018
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of electrical manholes from P Street to Q Street NW (west side).
-
Installation of electrical conduit from P Street to Q Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Friday, August 24, 2018
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of electrical manholes from P Street to Q Street NW (west side).
-
Installation of electrical conduit from P Street to Q Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, August 25, 2018
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of electrical manholes from P Street to Q Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Sunday, August 12 – Saturday, August 18, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, August 18th)
Sunday, August 12, 2018
-
No scheduled construction activity.
Monday, August 13, 2018
-
Installation of storm drain manhole from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit from P Street to Q Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Tuesday, August 14, 2018
-
Installation of storm drain manhole from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit from P Street to Q Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Wednesday, August 15, 2018
-
Installation of storm drain manhole from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit from P Street to Q Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Thursday, August 16, 2018
-
Installation of storm drain manhole from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit from P Street to Q Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Friday, August 17, 2018
-
Installation of storm drain manhole from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit from P Street to Q Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, August 18, 2018
-
Installation of storm drain manhole from N Street to Rhode Island Avenue NW (west side).
-
Installation of catch basin from Rhode Island Avenue to P Street NW (west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Sunday, August 5 – Saturday, August 11, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, August 11th)
Sunday, August 5, 2018
-
No scheduled construction activity.
Monday, August 6, 2018
-
Installation of electrical conduit from N Street to Rhode Island Avenue NW (west side).
-
Installation of electrical and storm drain manholes from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Tuesday, August 7, 2018
-
Installation of electrical conduit from N Street to Rhode Island Avenue NW (west side).
-
Installation of electrical and storm drain manholes from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Wednesday, August 8, 2018
-
Installation of electrical conduit from N Street to Rhode Island Avenue NW (west side).
-
Installation of electrical and storm drain manholes from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Thursday, August 9, 2018
-
Installation of electrical conduit from N Street to Rhode Island Avenue NW (west side).
-
Installation of electrical and storm drain manholes from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Friday, August 10, 2018
-
Installation of electrical conduit from N Street to Rhode Island Avenue NW (west side).
-
Installation of electrical and storm drain manholes from N Street to Rhode Island Avenue NW (west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, August 11, 2018
-
Installation of electrical conduit from N Street to Rhode Island Avenue NW (west side).
-
Installation of electrical and storm drain manholes from N Street to Rhode Island Avenue NW (west side).