Sunday, October 28 – Saturday, November 3, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, November 3rd)

Sunday, October 28, 2018

  • No scheduled construction activity.

Monday, October 29, 2018 - Friday, November 2, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Demolition and installation of sidewalks from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, November 3, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

Sunday, October 21 – Saturday, October 27, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, October 27th)

Sunday, October 21, 2018

  • No scheduled construction activity.

Monday, October 22, 2018

  • Saw cutting bumpouts N Street, Rhode Island Avenue and P Street (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Tuesday, October 23, 2018

  • Saw cutting bumpouts N Street, Rhode Island Avenue and P Street (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Wednesday, October 24, 2018

  • Saw cutting bumpouts N Street, Rhode Island Avenue and P Street (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Thursday, October 25, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Correction of curb and gutter from Thomas Circle to N Street (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Friday, October 26, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Correction of curb and gutter from Thomas Circle to N Street (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, October 27, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Sunday, October 14 – Saturday, October 20, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, October 20th)

Sunday, October 14, 2018

  • No scheduled construction activity.

Monday, October 15, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

Tuesday, October 16, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

Wednesday, October 17, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Correction of curb and gutter from Thomas Circle to N Street (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of 4X4 manhole at R Street NW for mainline.

  • Installation of electrical cables for streetlights from Rhode Island Avene To U Street. This installation will be done in a block by block sequence (east side and west side).

Thursday, October 18, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Correction of curb and gutter from Thomas Circle to N Street (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of 4X4 manhole at R Street NW for mainline.

  • Installation of electrical cables for streetlights from Rhode Island Avene To U Street. This installation will be done in a block by block sequence (east side and west side).

Friday, October 19, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Correction of curb and gutter from Thomas Circle to N Street (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of 4X4 manhole at R Street NW for mainline.

  • Installation of electrical cables for streetlights from Rhode Island Avene To U Street. This installation will be done in a block by block sequence (east side and west side).

Saturday, October 20, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Sunday, October 7 – Saturday, October 13, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, October 13th)

Sunday, October 7, 2018

  • No scheduled construction activity.

Monday, October 8, 2018

  • No construction activity scheduled due to the Columbus Day holiday. 

Tuesday, October 9, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

Wednesday, October 10, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

Thursday, October 11, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

Friday, October 12, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

Saturday, October 13, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Sunday, September 30 – Saturday, October 6, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, October 6th)

Sunday, September 30, 2018

  • No scheduled construction activity.

Monday, October 1, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree Removal from Thomas Circle to Q Street NW (east and west side).

Tuesday, October 2, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree Removal from Thomas Circle to Q Street NW (east and west side).

  • Correct curb and gutter from Thomas Circle to N Street (west side).

Wednesday, October 3, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree Removal from Thomas Circle to Q Street NW (east and west side).

  • Correct curb and gutter from Thomas Circle to N Street (west side).

Thursday, October 4, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree Removal from Thomas Circle to Q Street NW (east and west side).

  • Correct curb and gutter from Thomas Circle to N Street (west side).

Friday, October 5, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree Removal from Thomas Circle to Q Street NW (east and west side).

  • Correct curb and gutter from Thomas Circle to N Street (west side).

Saturday, October 6, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).