JUNE 2018

Sunday, June 24 – Saturday, June 30, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, June 30th)

Sunday, June 24, 2018
  • No scheduled construction activity.

Monday, June 25, 2018

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from Rhode Island Avenue to P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at Rhode Island Avenue NW (east side).

  • Installation of foundation for traffic signal cabinet at Rhode Island Avenue NW (east side).

  • Installation of ]catch basins at the corner of Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of traffic signal cabinet foundations (TC3, TC3,  TC5).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Tuesday, June 26, 2018

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from Rhode Island Avenue to P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at Rhode Island Avenue NW (east side).

  • Installation of foundation for traffic signal cabinet at Rhode Island Avenue NW (east side).

  • Installation of ]catch basins at the corner of Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of traffic signal cabinet foundations (TC3, TC3,  TC5).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Wednesday, June 27, 2018

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from Rhode Island Avenue to P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at Rhode Island Avenue NW (east side).

  • Installation of traffic signal pole on temporary foundation at P Street NW (east side).

  • Installation of foundation for traffic signal cabinet at P Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of traffic signal cabinet foundations (TC3, TC3,  TC5).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Thursday, June 28, 2018

  • Saw cutting and excavation for electrical conduit from T Street to Wallach Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from Wallach Street to U Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from P Street to Q Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at Q Street NW (east side).

  • Installation of foundation for traffic signal cabinet at P Street NW (east side).

  • Installation of foundation for traffic signal cabinet at R Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of traffic signal cabinet foundations (TC3, TC3,  TC5).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Friday, June 29, 2018

  • Saw cutting and excavation for electrical conduit from T Street to Wallach Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from Wallach Street to U Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from P Street to Q Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at Q Street NW (east side).

  • Installation of foundation for traffic signal cabinet at P Street NW (east side).

  • Installation of foundation for traffic signal cabinet at R Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of traffic signal cabinet foundations (TC3, TC3,  TC5).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Saturday, June 30, 2018

  • Saw cutting and excavation for electrical conduit from T Street to Wallach Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from Wallach Street to U Street NW (northbound lane).

  • Installation of traffic signal pole on temporary foundation at R Street NW (east side).

  • Installation of foundation for traffic signal cabinet at P Street NW (east side).

  • Installation of foundation for traffic signal cabinet at R Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

Sunday, June 17 – Saturday, June 23, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, June 23rd)

Sunday, June 17, 2018
  • No scheduled construction activity.

Monday, June 18, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation on Rhode Island Avenue NW (east side).

  • Installation of foundation of traffic signal cabinet on Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Tuesday, June 19, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation on Rhode Island Avenue NW (east side).

  • Installation of foundation of traffic signal cabinet on Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Wednesday, June 20, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation on Rhode Island Avenue NW (east side).

  • Installation of traffic signal pole on temporary foundation on P Street NW (east side).

  • Installation of foundation of traffic signal cabinet on P Street NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Thursday, June 21, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation on P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation on Q Street NW (east side).

  • Installation of foundation of traffic signal cabinet on Rhode Island Avenue NW (east side).

  • Installation of foundation of traffic signal cabinet on P Street NW (east side).

  • Installation of foundation of traffic signal cabinet on Q Street NW (east side).

  • Installation of foundation of traffic signal cabinet on R Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Friday, June 22, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation on P Street NW (east side).

  • Installation of traffic signal pole on temporary foundation on Q Street NW (east side).

  • Installation of foundation of traffic signal cabinet on Rhode Island Avenue NW (east side).

  • Installation of foundation of traffic signal cabinet on P Street NW (east side).

  • Installation of foundation of traffic signal cabinet on Q Street NW (east side).

  • Installation of foundation of traffic signal cabinet on R Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

  • Installation of Handbox (HB01 & HB02) at the corner of N Street NW (east side).

  • Installation of Handbox (HB08) at the corner of N Street NW (east side).

Saturday, June 23, 2018

  • Installation of traffic signal pole on temporary foundation on R Street NW (east side).

  • Installation of foundation of traffic signal cabinet on Rhode Island Avenue NW (east side).

  • Installation of foundation of traffic signal cabinet on P Street NW (east side).

  • Installation of foundation of traffic signal cabinet on Q Street NW (east side).

  • Installation of foundation of traffic signal cabinet on R Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

Sunday, June 10 – Saturday, June 16, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, June 16th)

Sunday, June 10, 2018

  • No scheduled construction activity.

Monday, June 11, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

Tuesday, June 12, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

Wednesday, June 13, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

Thursday, June 14, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

Friday, June 15, 2018

  • Saw cutting and excavation for electrical conduit from S Street to T Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

Saturday, June 16, 2018

  • Installation of catch basins at the corner of Rhode Island Avenue NW (east side).

Sunday, June 3 – Saturday, June 9, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, June 9th)

Sunday, June 3, 2018

  • No scheduled construction activity.

Monday, June 4, 2018

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (west side).

  • Installation of catch basins from Rhode Island Avenue to P Street NW (west side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

Tuesday, June 5, 2018

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (west side).

  • Installation of catch basins from Rhode Island Avenue to P Street NW (west side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

Wednesday, June 6, 2018

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (west side).

  • Installation of catch basins from Rhode Island Avenue to P Street NW (west side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

 

Thursday, June 7, 2018

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Installation of street light foundations from Rhode Island Avenue to P Street NW (west side).

  • Installation of catch basins from Rhode Island Avenue to P Street NW (west side).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

Friday, June 8, 2018

  • Saw cutting and excavation for electrical conduit from R Street to Riggs Street NW (northbound lane).

  • Demolition of existing curb & gutter from Rhode Island to P Street NW (east side).

Saturday, June 9, 2018

  • No scheduled construction activity.

Temporary Lane Closures due to Gas Leak - June 1, 2018

An unmarked Washington Gas valve was hit during excavation for electrical conduit on the 14th Street NW Streetscape project causing a gas leak. The location of this incident was 14th and S Streets NW. Both northbound and southbound lanes were initially shut down from R to T Streets NW (12:05 pm). The southbound lane was reopened at 1:45 pm; however, the northbound lane remained closed. By 5:00 pm, both lanes had been reopened. The Metropolitan Police Department, Fire Department and Washington Gas were all on site working to reopen travel lanes and resolve the situation as safely and quickly as possible. We apologize for any inconvenience and thank you for your patience during this incident.