APRIL 2020
Sunday, April 19 – Saturday, April 25, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 25th.






Sunday, April 19, 2020
-
No scheduled construction activity.
Monday, April 20 - Friday, April 24, 2020
-
Permanent striping.
-
Installation of traffic delineators.
-
Replacement of foundation (base and pole) on Q Street NW.
-
Installation of inductive loop detector.
-
Installation of traffic signs.
-
Removal of existing traffic control cabinets.
Saturday, April 25, 2020
-
Installation of traffic delineators.
-
Replacement of foundation (base and pole) on Q Street NW.
-
Removal of existing traffic control cabinets.
Sunday, April 12 – Saturday, April 18, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 18th.






Sunday, April 12, 2020
-
No scheduled construction activity.
Monday, April 13 - Friday, April 17, 2020
-
Permanent striping.
-
Installation of traffic delineators.
-
Installation of bike racks and benches.
-
Installation of decorative shrouds.
-
Removal of existing foundations.
-
Replacement of foundation on Q Street NW.
-
Installation of traffic signs.
-
Streetlight switchovers.
-
Removal of existing traffic control cabinets.
-
Installation of communication cable on Florida Avenue NW from 13th Street to 14th Street.
Saturday, April 18, 2020
-
Streetlight switchovers.
Sunday, April 5 – Saturday, April 11, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, April 11th.






Sunday, April 5, 2020
-
No scheduled construction activity.
Monday, April 6 - Friday, April 10, 2020
-
Tree planting and landscaping.
-
Permanent striping.
-
Install decorative shrouds.
-
Install fixtures.
-
Pull communication cable and communication system switchover at Florida Avenue NW.
Saturday, April 11, 2020
-
No scheduled construction activity at this time (subject to change).
Sunday, March 29 – Saturday, April 4, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 4th.






Sunday, March 29, 2020
-
No scheduled construction activity.
Monday, March 30 - Friday, April 3, 2020
-
Removing trees.
-
Milling and paving on Florida Avenue, V Street and W Street NW.
-
Permanent striping.
-
Install decorative shrouds.
-
Install fixtures.
-
Replace existing with new fixtures between V Street and W Street NW.
-
Splicing manholes from T Street to Florida Avenue NW.
-
Street light switchover.
Saturday, April 4, 2020
-
Install decorative shrouds.
-
Install fixtures.
-
Splicing manholes from T Street to Florida Avenue NW.
-
Street light switchover.