Sunday, November 25 – Saturday, December 1, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, December 1st)

Sunday, November 25, 2018

  • No scheduled construction activity.

Monday, November 26, 2018 - Wednesday, November 28, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from Rhode Island Avenue to P Street NW (west side).

  • Installation of electrical conduit and manholes from W Street to V Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of foundations for TEC cabinets from R Street to Florida Avenue NW (east and west side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Thursday, November 29, 2018 - Friday, November 30, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from Rhode Island Avenue to P Street NW (west side).

  • Installation of electrical conduit and manholes from W Street to V Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of foundations for TEC cabinets from R Street to Florida Avenue NW (east and west side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, December 1, 2018

  • No scheduled construction activity.

Sunday, November 18 – Saturday, November 24, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, November 24th)

Sunday, November 18, 2018

  • No scheduled construction activity.

Monday, November 19, 2018 - Wednesday, November 21, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Demolition and installation of sidewalks from Rhode Island Avenue to P Street NW (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of manhole at R Street NW for mainline.

  • Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of foundations for TEC cabinets from R Street to Florida Avenue NW (east and west side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Thursday, November 22, 2018 - Friday, November 23, 2018

  • No scheduled construction activity - Thanksgiving Day observed.

Saturday, November 24, 2018

  • No scheduled construction activity.

Sunday, November 11 – Saturday, November 17, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, November 17th)

Sunday, November 11, 2018

  • No scheduled construction activity.

Monday, November 12, 92018

  • No scheduled construction activity - Veterans Day observed.

Tuesday, November 13, 2018 - Friday, November 16, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Demolition and installation of sidewalks from Rhode Island Avenue to P Street NW (east side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of manhole at R Street NW.

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, November 17, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Sunday, November 4 – Saturday, November 10, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, November 10th)

Sunday, November 4, 2018

  • No scheduled construction activity.

Monday, November 5, 2018 - Tuesday, November 6, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Wednesday, November 7, 2018 - Friday, November 9, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Tree removals from Thomas Circle to Q Street NW (east and west side).

  • Demolition and installation of sidewalks from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).

  • Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, November 10, 2018

  • Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).

  • Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).