SEPTEMBER 2019
Sunday, September 22 – Saturday, September 28, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, September 28th.
Sunday, September 22, 2019
-
No scheduled construction activity.
Monday, September 23 - Saturday, September 28, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of curb and sidewalk at 14th and U Street NW (Monday - Wednesday).
-
Installation of bumpout and sidewalk between T Street and U Street NW (east side; Wednesday to Friday).
-
Installation of bus island at 14th and Rhode Island Avenue NW (Monday
-
Begin electric line on 14th and R Street NW.
-
Pulling of conductor and push buttons at N Street, P Street, Q Street, V Street and W Street NW.
-
Installation of two 20-ft poles and four 28-ft poles for traffic work.
-
Installation of curb and sidewalk at U Street NW (Friday and Saturday).
SPECIAL NOTICE: 14th St. NW between R St. and S St. NW
Washington Gas had to close 14th St. NW between R St. and S St. NW on September 17th due to a utility issue. This closure was not a part of the 14th Street NW Streetscape project. All lanes are reopened at this time.
Sunday, September 15 – Saturday, September 21, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, September 21st.
Sunday, September 15, 2019
-
No scheduled construction activity.
Monday, September 16 - Saturday, September 21, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Begin electric line on 14th and R Street NW.
-
Pulling of conductor and push buttons at N Street, P Street, Q Street, V Street and W Street NW.
-
Installation of two 20-ft poles and four 28-ft poles for traffic work.
-
Installation of curb and sidewalk at U Street NW (Friday and Saturday).
Sunday, September 8 – Saturday, September 14, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There was no work performed on Saturday, September 14th.
Sunday, September 8, 2019
-
No scheduled construction activity.
Monday, September 9 - Friday, September 13, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Excavation for bus island at 14th and R Street NW at the curb parking lane/sidewalk.
-
Removal of existing signs and installation of new signs from Q Street to R Street NW.
-
Saw cuting of existing PCC pavement and preparation of PCC placement including placement of granite curb and brick gutter at the northwest corner of 14th and Florida Avenue NW.
-
Pulling of conductor/push buttons at N Street, P Street, Q Street, V Street W Street and Florida Avenue NW.
Saturday, September 14, 2019
-
No construction activity.
Sunday, September 1 – Saturday, September 7, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, September 7th.
Sunday, September 1, 2019
-
No scheduled construction activity.
Monday, September 2, 2019
-
No scheduled construction activity due to the Labor Day Holiday.
Tuesday, September 3 - Friday, September 6, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of bump out and sidewalk from T Street to U Street NW (east side).
-
Installation of curb and sidewalk at W Street and Florida Avenue NW (this work is scheduled to take place on the west side on Friday).
-
Installation of curb and sidewalk at U Street NW (this work is scheduled to take place on Friday).
-
Watermain work at 14th & R Street NW.
-
Shutdown for watermain between T Street and U Street NW (per DC Water scheduled).
-
Pulling of conductor/push buttons at N Street, P Street, Q Street, V Street W Street and Florida Avenue NW.
-
Splicing of manholes from Thomas Circle to Rhode Island Avenue NW.
-
Pulling cable for traffic poles and video detection cameras.
Saturday, September 7, 2019
-
Pulling of conductor/push buttons at N Street, P Street, Q Street, V Street W Street and Florida Avenue NW.
-
Splicing of manholes from Thomas Circle to Rhode Island Avenue NW.
-
Pulling cable for traffic poles and video detection cameras.