AUGUST 2019
Sunday, August 25 – Saturday, August 31, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, August 31st.
Sunday, August 18 – Saturday, August 24, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, August 24th.
Sunday, August 18, 2019
-
No scheduled construction activity.
Monday, August 19 - Friday, August 23, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of sidewalk drains and sidewalk at 1819-1827 14th Street NW.
-
Installation of bump out and sidewalk from T Street to U Street NW (east side).
-
Installation of curb and sidewalk from Wallach Place to U Street NW (this work is scheduled to take place on the east side on Monday, Tuesday and Wednesday).
-
Watermain work at 14th & R Street NW.
-
Installation of light pole and ADA ramp at W Street NW (scheduled to place on Monday and Tuesday only).
-
Shutdown for watermain between T Street and U Street NW (per DC Water scheduled).
-
Installation of bus island at 14th & U Street NW.
-
Installation of push buttons from R Street to Florida Avenue NW.
-
Paving from P Street to Corcoran Street NW.
-
Pulling cable for traffic poles and video detection cameras.
-
Tree removal at the southewest corner of Rhode Island Avenue and the southeast corner of T Street NW.
Saturday, August 24, 2019
-
Installation of bus island at 14th & U Street NW.
-
Installation of bolt-on UPS systems at traffic control cabinets from R Street to Florida Avenue NW.
-
Installation of push buttons from R Street to Florida Avenue NW.
-
Pulling cable for traffic poles and video detection cameras.
Sunday, August 11 – Saturday, August 17, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, August 17th.
NIGHTTIME MILLING AND PAVING WORK SUSPENDED AS OF TUESDAY, AUGUST 13TH
Sunday, August 11, 2019
-
No scheduled construction activity.
Monday, August 12 - Friday, August 16, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of bump out and sidewalk from T Street to U Street NW (east side).
-
Installation of curb and sidewalk from T Street to Wallach Place NW (east side).
-
Installation of curb and sidewalk from Wallach Place to U Street NW (this work is scheduled to take place on the east side on Monday, Tuesday and Wednesday).
-
Installation of bus island at the southeast corner of T Street NW.
-
Installation of bus island at 14th & U Street NW.
-
Watermain work at 14th & R Street NW.
-
Installation of light pole and ADA ramp at W Street NW (scheduled to place on Monday and Tuesday only).
-
Shutdown for watermain between T Street and U Street NW (per DC Water scheduled).
-
Installation of push buttons from R Street to Florida Avenue NW.
-
Milling and paving from P Street to Corcoran Street NW.
-
Permanent Striping from P Street to Corcoran Street NW.
-
Pulling cable for traffic poles and video detection cameras.
-
Tree removal at the southewest corner of Rhode Island Avenue and the southeast corner of T Street NW.
Saturday, August 17, 2019
-
Installation of bus island at 14th & U Street NW.
-
Installation of bolt-on UPS systems at traffic control cabinets from R Street to Florida Avenue NW.
-
Installation of push buttons from R Street to Florida Avenue NW.
-
Pulling cable for traffic poles and video detection cameras.
Sunday, August 4 – Saturday, August 10, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, August 10th.
PLEASE EXPECT DELAYS DUE TO NIGHTTIME MILLING AND PAVING WORK
(P Street to R Street NW from 7pm - 5am)
Sunday, August 4, 2019
-
No scheduled construction activity.
Monday, August 5 - Friday, August 9, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of bump out and sidewalk from T Street to U Street NW (east side).
-
Installation of curb and sidewalk from T Street to Wallach Place NW (east side).
-
Installation of bus island at 14th & P Street NW (northbound).
-
Installation of bus island at 14th & U Street NW.
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Shutdown for watermain between T Street and U Street NW (per DC Water scheduled).
-
Installation of push buttons from R Street to Florida Avenue NW.
-
Milling and paving from P Street to R Street NW.
-
Pulling cable for traffic poles and video detection cameras.
-
Tree removal at the southewest corner of Rhode Island Avenue NW.
-
Tree removal at the southeast corner of T Street NW.
Saturday, August 10, 2019
-
Installation of bus island at 14th & U Street NW.
-
Installation of bolt-on UPS systems at traffic control cabinets from R Street to Florida Avenue NW.
-
Installation of push buttons from R Street to Florida Avenue NW.
-
Paving from P Street to Corcoran Street NW
-
Pulling cable for traffic poles and video detection cameras.