top of page

AUGUST 2019

Sunday, August 25 – Saturday, August 31, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, August 31st.

Sunday, August 18 – Saturday, August 24, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, August 24th.

Sunday, August 18, 2019

  • No scheduled construction activity.

 

Monday, August 19 - Friday, August 23, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Installation of sidewalk drains and sidewalk at 1819-1827 14th Street NW.

  • Installation of bump out and sidewalk from T Street to U Street NW (east side).

  • Installation of curb and sidewalk from Wallach Place to U Street NW (this work is scheduled to take place on the east side on Monday, Tuesday and Wednesday).

  • Watermain work at 14th & R Street NW.

  • Installation of light pole and ADA ramp at W Street NW (scheduled to place on Monday and Tuesday only).

  • Shutdown for watermain between T Street and U Street NW (per DC Water scheduled).

  • Installation of bus island at 14th & U Street NW.

  • Installation of push buttons from R Street to Florida Avenue NW. 

  • Paving from P Street to Corcoran Street NW.

  • Pulling cable for traffic poles and video detection cameras. 

  • Tree removal at the southewest corner of Rhode Island Avenue and the southeast corner of T Street NW.

Saturday, August 24, 2019

  • Installation of bus island at 14th & U Street NW. 

  • Installation of bolt-on UPS systems at traffic control cabinets from R Street to Florida Avenue NW.

  • Installation of push buttons from R Street to Florida Avenue NW.

  • Pulling cable for traffic poles and video detection cameras.  

Sunday, August 11 – Saturday, August 17, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, August 17th.

NIGHTTIME MILLING AND PAVING WORK SUSPENDED AS OF TUESDAY, AUGUST  13TH

Sunday, August 11, 2019

  • No scheduled construction activity.

 

Monday, August 12 - Friday, August 16, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Installation of bump out and sidewalk from T Street to U Street NW (east side).

  • Installation of curb and sidewalk from T Street to Wallach Place NW (east side).

  • Installation of curb and sidewalk from Wallach Place to U Street NW (this work is scheduled to take place on the east side on Monday, Tuesday and Wednesday).

  • Installation of bus island at the southeast corner of T Street NW.

  • Installation of bus island at 14th & U Street NW.

  • Watermain work at 14th & R Street NW.

  • Installation of light pole and ADA ramp at W Street NW (scheduled to place on Monday and Tuesday only).

  • Shutdown for watermain between T Street and U Street NW (per DC Water scheduled).

  • Installation of push buttons from R Street to Florida Avenue NW. 

  • Milling and paving from P Street to Corcoran Street NW.

  • Permanent Striping from P Street to Corcoran Street NW.

  • Pulling cable for traffic poles and video detection cameras. 

  • Tree removal at the southewest corner of Rhode Island Avenue and the southeast corner of T Street NW.

Saturday, August 17, 2019

  • Installation of bus island at 14th & U Street NW. 

  • Installation of bolt-on UPS systems at traffic control cabinets from R Street to Florida Avenue NW.

  • Installation of push buttons from R Street to Florida Avenue NW.

  • Pulling cable for traffic poles and video detection cameras.  

Sunday, August 4 – Saturday, August 10, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, August 10th.

PLEASE EXPECT DELAYS DUE TO NIGHTTIME MILLING AND PAVING WORK

(P Street to R Street NW from 7pm - 5am)

Sunday, August 4, 2019

  • No scheduled construction activity.

 

Monday, August 5 - Friday, August 9, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).

  • Installation of bump out and sidewalk from T Street to U Street NW (east side).

  • Installation of curb and sidewalk from T Street to Wallach Place NW (east side).

  • Installation of bus island at 14th & P Street NW (northbound).

  • Installation of bus island at 14th & U Street NW.

  • Installation of additional 4X4 manhole via RFI at 14th & R Street NW.

  • Installation of streetlight and traffic signal foundations at S Street and T Street NW.

  • Watermain work at 14th & R Street NW.

  • Shutdown for watermain between T Street and U Street NW (per DC Water scheduled).

  • Installation of push buttons from R Street to Florida Avenue NW. 

  • Milling and paving from P Street to R Street NW.

  • Pulling cable for traffic poles and video detection cameras. 

  • Tree removal at the southewest corner of Rhode Island Avenue NW.

  • Tree removal at the southeast corner of T Street NW.

Saturday, August 10, 2019

  • Installation of bus island at 14th & U Street NW. 

  • Installation of bolt-on UPS systems at traffic control cabinets from R Street to Florida Avenue NW.

  • Installation of push buttons from R Street to Florida Avenue NW.

  • Paving from P Street to Corcoran Street NW 

  • Pulling cable for traffic poles and video detection cameras.  

bottom of page