JANUARY 2019

Sunday, January 27 – Saturday, February 2, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, February 2nd)

Sunday, January 27, 2019

  • No scheduled construction activity.

Monday, January 28 - Friday, February 1, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from P Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from P Street to R Street NW (east side).

  • Installation of electrical conduit and manholes at U Street NW (east and west side).

  • Installation of fire hydrant at S Street NW, T Street NW, Church Street NW and Swann Street NW.

  • Installation of foundations for TEC cabinets at Q Street, R Street, S Street, T Street, U Street, V Street and Florida Avenue NW.

  • Installation of TEC cabinets at N Street, P Street, W Street, Wallach Place and Rhode Island Avenue NW.

  • Installation of streetlight and traffic signal foundations from U Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, February 2, 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress.

Sunday, January 20 – Saturday, January 26, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, January 26th)

Sunday, January 20, 2019

  • No scheduled construction activity.

Monday, January 21, 2019

  • No construction activity due to Martin Luther King, Jr. Holiday.

 

Tuesday, January 22 - Friday, January 25, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from P Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from P Street to R Street NW (east side).

  • Installation of electrical conduit and manholes at U Street NW (east and west side).

  • Installation of fire hydrant at S Street, T Street, Church Street and Swann Street NW.

  • Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of foundations for Traffic Control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street and Florida Avenue NW.

  • Installation of TEC cabinets at N Street, P Street, W Street, Wallach Place and Rhode Island Avenue NW.

  • Installation of streetlight and traffic signal foundations from U Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, January 26 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress.

Sunday, January 13 – Saturday, January 19, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, January 19th)

Sunday, January 13, 2019

  • No scheduled construction activity.

Monday, January 14 - Friday, January 18, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from P Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Demolition and installation of sidewalks from P Street to R Street NW (east side).

  • Installation of electrical conduit and manholes at U Street NW (east and west side).

  • Installation of fire hydrant at Church Street and Swann Street NW.

  • Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of foundations for Traffic Control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street and Florida Avenue NW.

  • Installation of foundation and TEC cabinet at the southeast corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from U Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, January 19, 2019

  • All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress.

Sunday, January 6 – Saturday, January 12, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, January 12th)

Sunday, January 6, 2019

  • No scheduled construction activity.

Monday, January 7 - Friday, January 11, 2019

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from P Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).

  • Installation of fire hydrant at Church Street and Swann Street NW.

  • Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of foundations for Traffic Control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street and Florida Avenue NW.

  • Installation of foundation and TEC cabinet at the southeast corner of U Street NW.

  • Installation of streetlight and traffic signal foundations from U Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

Saturday, January 12, 2019

  • No scheduled construction activity.

Sunday, December 30 – Saturday, January 5, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, January 5th)

Sunday, December 30, 2018

  • No scheduled construction activity.

Monday, December 31, 2018 - Tuesday, January 1, 2019

  • No scheduled construction activity due to New Year's Day Holiday.

Wednesday, January 2, 2019 - Friday, January 4, 2019

  • Demolition and installation of sidewalks from P Street to Q Street NW (east side).

  • Installation of electrical conduit and manholes from U Street to V Street NW (west side).

  • Installation of catch basins at Riggs Street NW (east side).

Saturday, January 5, 2019

  • No scheduled construction activity.