JUNE 2019
Sunday, June 23 – Saturday, June 29, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, June 29th.
Sunday, June 23, 2019
-
No scheduled construction activity.
Monday, June 24 - Friday, June 28, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of curb and sidewalk from S Street to T Street NW (east side).
-
Installation of bus island at 14th & Rhode Island Avenue NW (east side).
-
Installation of bus island at 14th & N Street NW (east side).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW (scheduled to take place on Monday).
-
Tree trimming at the southwest corner of Rhode Island Avenue NW (scheduled to take place on Monday and Wednesday).
Saturday, June 29, 2019
-
No scheduled construction activity.
Sunday, June 16 – Saturday, June 22, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, June 22nd.
Sunday, June 16, 2019
-
No scheduled construction activity.
Monday, June 17 - Friday, June 21, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of curb and sidewalk from 14th & V Street toward 14th & U Street NW (east side).
-
Installation of catch basin at 14th & T Street NW.
-
Installation of catch basin at 14th & S Street NW.
-
Removal of bus shelters starting from 14th & R Street NW (heading north).
-
Installation of bus island at 14th & N Street NW (east side).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Reconnecting for water service at T Street to U Street NW (west side).
-
Shutdown of watermain between 14th Street and T Street NW (per DC Water's schedule).
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
-
Tree trimming at the southwest corner of Rhode Island Avenue NW (scheduled to take place on Monday and Wednesday).
-
Tree trimming at the northeast corner of T Street NW (scheduled to take place on Monday and Wednesday).
Saturday, June 22, 2019
-
No scheduled construction activity.
Sunday, June 9 – Saturday, June 15, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, June 15th.
Sunday, June 9, 2019
-
No scheduled construction activity.
Monday, June 10 - Friday, June 14, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of curb and sidewalk from 14th & V Street toward 14th & U Street NW (east side).
-
Installation of catch basin at 14th & T Street NW.
-
Installation of catch basin at 14th & S Street NW.
-
Removal of bus shelters starting from 14th & P Street NW (heading north).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Reconnecting for water service from T Street to U Street NW (west side).
-
Shutdown of watermain between 14th Street and T Street NW (per DC Water's schedule).
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
Saturday, June 15, 2019
-
No scheduled construction activity.
Sunday, June 2 – Saturday, June 8, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, June 8th.
Sunday, June 2, 2019
-
No scheduled construction activity.
Monday, June 3 - Friday, June 7, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of curb and sidewalk from 14th & U Street toward 14th & Florida Avenue NW.
-
Installation of fire hydrants at S Street NW.
-
Installation of catch basins at 14th & S Street NW (scheduled to take place on Friday).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Reconnecting for water service at T Street to U Street NW (west side).
-
Shutdown of watermain between 14th Street and T Street NW (per DC Water's schedule).
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
Saturday, June 8, 2019
-
No scheduled construction activity.